Project Timeline

2026

February 10

Incidental Take Permit

February 9

NPPD received the necessary Record of Decision from the U.S. Fish and Wildlife Service, allowing construction to begin on the R-Project.

2022

November 17–December 19

U.S. Fish & Wildlife Service public comment period for Supplemental Environmental Impact Statement scope

2020

June

Project construction paused when the federal district court for the District of Colorado vacated the Incidental Take Permit

February

Began substation construction and distribution line relocations

2019

July

Began pre-construction activities

June 12

Habitat conservation plan approved: Incidental take permit issued

January 10

Awarded construction contracts to Forbes Bros. Timberline Construction, Inc.

2017

September 8–November 7

Second U.S. Fish & Wildlife Service public comment period on the Draft Environmental Impact Statement of the R-Project transmission line

May 12–July 11

First U.S. Fish & Wildlife Service public comment period on the Draft Environmental Impact Statement of the R-Project transmission line

2016

November 14–17

Conducted Community Conversation Meetings

2015

December

Began easement acquisition

July 7

Memorandum of Understanding between NPPD and U.S. Fish & Wildlife Service executed for preparation of Habitat Conservation Plan and Environmental Impact Statement

January 20

Final route announced via letters to landowners

2014

November 4, 6, 10, 12

NPPD Public Hearings in Logan, Lincoln, Thomas, Blaine, Garfield, Loup, Wheeler and Holt Counties

October 10

Nebraska Power Review Board approves project

May 19

Southwest Power Pool approves Notice to Construct

April 29–30, May 1, 5–7

NPPD Open Houses on Alternative & Preferred Line Routes in Stapleton, Sutherland, Thedford, Bartlett, Dunning and Burwell

2013

September 9–11, 16–17

NPPD Open Houses on Corridors in Thedford, Sutherland, Dunning, Stapleton, Burwell and Bartlett

January 14–17, 21–22

NPPD Open Houses on Study Area in Tryon, Hershey, Halsey, Mullen, Chambers and Ainsworth

2012

April 19

Southwest Power Pool approved Notice to Construct (with Conditions)